ASTANA / BEIJING - October 2026 - Samruk-Energy JSC, the energy arm of Kazakhstan's sovereign wealth fund Samruk-Kazyna, and China Energy International Group (Energy China) held high-level talks in late October 2026 to review the construction progress of their joint 300 MW photovoltaic power plant in the Turkestan region. During the meeting, both parties confirmed that approximately 70% of the photovoltaic modules have already been installed at the site, keeping the flagship renewable asset on track for first grid connection in December 2026 and full commercial operation in the first quarter of 2027.
The talks were led by Kairat Maxutov, Chairman of the Management Board of Samruk-Energy, and Lin Xiaodan, Chairman of the Board of China Energy Overseas Investment Co., Ltd. (Energy China's overseas investment platform). The delegations reviewed the remaining construction, installation and commissioning milestones, and agreed on measures to secure resource availability and maintain the project schedule .
Project at a Glance
Location: Sauran district, Turkestan region, Kazakhstan (approx. 30 km from Shymkent)
Capacity: 300 MW AC photovoltaic + 90 MW / 360 MWh battery energy storage system (BESS)
Area: ~800 hectares, with ~600,000 next-generation bifacial modules on single-axis trackers
Investment: ~USD 307 million
Expected output: ~674 million kWh of clean electricity per year
Grid link: 220 kV step-up substation and overhead line to the Kentau substation
Partners: Qazaq Green Power PLC (Samruk-Energy subsidiary) and China Energy Overseas Investment Co., Ltd.
Once energised, the plant will become Kazakhstan's largest single-site solar-plus-storage facility currently under construction and the first utility-scale "PV + BESS" project in the country. The storage component is designed to smooth output volatility, reduce curtailment and strengthen grid reliability in the southern power zone, which has faced seasonal supply constraints .
Milestones Reached Ahead of Schedule
Construction officially moved into the main phase in May 2026 with the first pile foundation pour. By July, module mounting had begun alongside foundation works for the main transformer, BESS and switchgear. The October review confirmed that module installation has since advanced to the 70% mark, with the step-up substation building topped out in August and electromechanical works now underway .
"Reaching 70% module installation before the end of October gives us a realistic buffer ahead of the December energisation window," a joint project spokesperson noted. "The focus now shifts to completing the BESS integration, 220 kV connection tests and protection-system commissioning so that first power flows before year-end."
Strategic Context
The Turkestan solar plant is the first project launched under the Kazakhstan–China intergovernmental agreement on renewable energy signed in Baku in November 2024 and ratified by President Kassym-Jomart Tokayev in March 2026. That framework covers 1.8 GW of renewables across Turkestan, Karaganda and Pavlodar regions, including a 500 MW wind farm in Karaganda also being advanced by Samruk-Energy and Energy China .
For Astana, the asset supports the Strategy Kazakhstan 2050 target of raising renewables to 50% of the energy balance and cuts reliance on coal-fired generation in the south. For Beijing, it is Energy China's first invested renewable project in Kazakhstan and a anchor entry under the Belt and Road green-energy corridor .
Local Impact
During peak construction the site has employed around 500 workers, with local hiring and Turkestan-region suppliers prioritised. Both sides used the October meeting to explore expanding the share of Kazakhstan-manufactured equipment in remaining packages and to lock in project financing for the BESS and transmission scope .
What Comes Next
Nov–Dec 2026: Complete module strings, BESS container placement, 220 kV line stringing
Dec 2026: First synchronisation / test generation onto the Kentau grid
Jan–Mar 2027: Reliability runs, PPA-backed commercial operation date (COD)
Beyond: Joint feasibility work on a 1 GW wind + storage cluster in Zhetysu region, plus the 500 MW Karaganda wind farm targeting first power in 2028
"Both boards reaffirmed their commitment to the agreed deadlines and to regular milestone monitoring," the Samruk-Energy statement said after the talks. "The partnership is not limited to this site - it is becoming the operating model for Kazakhstan–China renewable cooperation through 2029."
About Samruk-Energy JSC
Samruk-Energy is the vertically integrated energy holding of Samruk-Kazyna, Kazakhstan's sovereign wealth fund, managing coal, gas, hydro, wind, solar and grid assets nationwide.
About China Energy International Group
China Energy International Group is the overseas investment and EPC arm of China Energy Engineering Corporation (CEEC), one of the world's largest energy infrastructure contractors, with over USD 8 billion of projects tracked in Kazakhstan alone.